The Federal Government has reaffirmed its commitment to completing the 750-kilometre Lagos-Calabar Coastal Highway, disclosing plans to integrate about 400 kilometres of the East-West Road into a broader transport network spanning parts of the Niger Delta.
Minister of Works, Dave Umahi, said surveying and design activities were ongoing across Edo, Delta, Bayelsa and Rivers states, dismissing concerns that the coastal highway had been abandoned or its overall scope altered.
Umahi explained that the proposed East-West Road integration was intended to improve connectivity across the coastal corridor and address weaknesses in existing infrastructure, including sections vulnerable to flooding.
According to him, the government has sought President Bola Tinubu’s approval to incorporate the 400-kilometre East-West Road stretch, which extends through Edo, Delta, Akwa Ibom and Cross River states, into the wider infrastructure development programme.
He noted that parts of the existing road were constructed below flood levels, leaving sections exposed to damage during heavy rainfall and rising water levels.
The minister cited damage to portions of the road around Abaro in Delta State, where flooding recently affected several locations, as an example of the challenges facing the corridor.
He said the proposed intervention would complement the coastal highway and improve the integration of road infrastructure across the South-South region.
Umahi stressed that the 750-kilometre Lagos-Calabar Coastal Highway remained an ongoing project, adding that designers and surveyors were working to establish the required alignments across the affected states.
Providing an update on construction, the minister said the 47.47-kilometre first section in Lagos had been completed, while work on Section Two, covering 55 kilometres, was progressing towards the target of completing pavement works by mid-November.
He also reported ongoing construction on Sections 3A and 3B, covering approximately 75 kilometres, with progress exceeding 40 per cent in parts of the Cross River and Akwa Ibom corridor, according to his briefing.
Construction is also continuing on Sections 4A and 4B along the Ogun-Ondo axis, while work on Section Five in Akwa Ibom has reportedly exceeded 20 per cent.
Umahi said the coastal highway was designed as an investment-driven infrastructure project intended to improve transportation, stimulate economic activity and strengthen links between communities and commercial centres.
He added that the government’s broader legacy road programme was being expanded to improve connections between Nigeria’s geopolitical zones.
The minister maintained that the coastal highway’s planned length and overall objective remained unchanged, describing the East-West Road proposal as part of efforts to create a more integrated and resilient transport network.
However, the proposed integration will require clear details on the final alignment, funding arrangements and the scope of rehabilitation required on existing roads to establish how the two corridors will operate together.